The job
April 2026, Kandla, India. Three bunker tanks on a ship at Kandla needed the sludge taken out. The work was done by a shore gang.
Why bunker tanks collect sludge
Heavy fuel oil carries water, sediment and heavy hydrocarbon fractions that settle in the bottom of a bunker tank over time. As the sludge layer grows it reduces usable capacity and risks fouling suctions and purifiers, and it has to come out before tank inspections or repairs.
It is enclosed-space work in every sense: the tank is ventilated and the atmosphere tested before anyone enters, monitored while they work, and the sludge is removed and kept for disposal through a reception facility rather than anywhere it should not go.
Result
Sludge removed from three bunker tanks by a shore gang at Kandla, April 2026.
The service behind it
Tank Cleaning
Cargo and slop tank cleaning for DPP and CPP trades, demucking, shore terminal tanks and offshore vessel tankage.
Full service detailsGuides for this job
- "Visually clean or water white? Agreeing the cleanliness standard before inspection"
What common tank cleanliness standards mean in practice, why the standard must be agreed before cleaning starts, and how to avoid disputes at the inspection.
- "Gas-freeing without ship's power: planning tank work on a dead ship"
How to plan gas-freeing and tank cleaning on a tanker with limited or no power, including portable fans, power supply, inert gas, atmosphere monitoring and safety controls.
- "Converting CPP tanks to wall wash standard: when it's needed and what it takes"
When charterers ask for wall wash standard on product tankers, what extra preparation it needs beyond a normal clean product standard, and how to plan the time and effort.